Unit 4 Maintaining the Dimensional Accuracy of Construction Work



Introduction

Section 1. Obtaining Information

Section 2. Establish Lines and Levels


Section 3. Inaccurate or Missing Information

 

Information and Guidance is available on how you should study

Study Guide
 


Assignment for Unit 4



Before Submitting your assignment you MUST read and conform to
 

Instructions for

Submitting Assignments



 

Additional Learning Resourses

Constructionsite

 


 






 
Additional Information

You should relate your responses to any of the tasks set in this unit to the documents listed below; these will provide information about the type and size of the project.  



























Section 1























 
























































































































































 
Section 2















































































































































 
 




































































































































































































































































































































































 















































































 
Section 3




























































































































































 
 

Unit aim: This unit is designed to meet the needs of construction Site Supervisors in order to maintain the dimensional accuracy of the works.
 


This unit has an Introduction and is divided into 3 study sections.

Introduction

Section 1 Obtaining Information

4.1.1 Identify the roles and responsibilities of the contracting parties for dimensional quality control.
4.1.2 Identify the sources of the relevant setting out information
4.1.3 Obtain the relevant setting out information
4.1.4 Identify permanent and temporary benchmarks and setting out points.
4.1.5 Check the setting out points against the setting out information for the works.


Section 2 Establish Lines and Levels

4.2.1 Relate the setting out information to the circumstances of the site.
4.2.2 Set out lines and levels for construction operations. 
4.2.3 Determine the lengths of travellers for excavation and concreting.


Section 3 Inaccurate or Missing Information

4.3.1 Check that the setting out information in the contract documents is mutually consistent and consistent with the site dimensions.
4.3.2 Inform any interested parties of any inaccurate or missing setting out information.


Unit Recommended Reading

Irvine, W and MacLennan, F (2005) Surveying for Construction, (5th Ed), McGrew Hill, Oxford


Books can be ordered from most bookshops or online from Amazon.


Studying
 
Before starting you should read the ‘Study Guide’ accessible from the link on the left.
 


Introduction

The unit is intended to introduce the learner to the setting out processes for buildings and structures and provide knowledge, understanding and practical ability in basic surveying procedures.

This learning package requires the learner to complete some of the unit content by practical means and exercises. The course includes the need to attend a two day practical group on the dates determined by the award providers.

Prior to attending the practical workshop the learner will complete the sections of this unit and obtain a pass in the e-learning aspects.
 
                  

Please Note

All information contained in this Study Unit was considered correct at the time of writing but Students must not rely on information contained in the Study Unit and/or references for any purposes other than use within this CIOB qualification aim as legislation and working practices are constantly being revised and updated. Students are advised therefore to continually up-date themselves as to current legislation and construction practice and must not to rely on information contained within the Study Unit and/or references for practical applications in the workplace. Where legislation or construction practice has been superseded to that contained in the Study Unit Students should note this within their responses to the tasks.

 


Section 1 Obtaining Information

Learning outcome: On completion the learner will know how to obtain setting out information and check dimensional controls.
 
 

Contents
 
4.1.1 Identify the roles and responsibilities of the contracting parties for dimensional quality control.
4.1.2 Identify the sources of the relevant setting out information.
4.1.3 Obtain the relevant setting out information.


  

4.1.1 Identify the roles and responsibilities of the contracting parties for dimensional quality control

Setting out information is obtained from everyone who has been a part of the project from inception; this may initially be the client and their advisors who will have considered the size and form of construction needed and will undoubtedly have produced outline sketches of the building and its plan on site. All will have their ideas as to how the structure will fit onto the site and how much circulation and infrastructure land will be required. The final layout plans and details being produced by professionals working within the construction industry usually Architects and /or Engineers.
 
 

4.1.2 Identify the sources of the relevant setting out information

Plans will have been drawn up by the Engineer and Architect which position the structures on the site in an exact orientation and at an exact level. The position and level will have a direct relationship to fixed and immovable points on or around the site which can be re-established during the actual site setting out process.
 
The plans will have been submitted to the Local Authority and approval to construct granted before the setting out of the site commences.
 
The Site Manager will carry out checks on site and on the drawings and details to ensure that as far as is reasonable these are dimensionally accurate and the levels compatible with those of the final structure. Never scale from the layout drawings in order to determine dimensions. Setting out grids where provided by the Architect and /or Engineer are very useful in establishing setting out details but these are not always present.
 
It is the Architect and /or Engineer’s responsibility to ensure that all necessary setting out information is available; the setting out Engineer or Site Manager should not attempt to set out the building unless this information has been provided.
 
Many companies will use specialist setting out Engineers on large contracts. However a competent Site Manager should be capable of setting out all but the largest and most complex of buildings and must be able to carry out levelling and setting out subsequent to that of the Engineers.
 
This will be dealt with further in Section 4.3.1.
 


4.1.3 Obtain the relevant setting out information

The building setting out will be strictly in accordance with the details and drawings issued by the Architect and /or Engineer; any discrepancies between these drawing and documents should have been identified prior to commencement of the site setting out and clarified in writing by the Contractor. Any discrepancies identified at the site setting out stage should be referred to the Architect and /or Engineer for clarification.
 
The type of information needed will include:  
The setting out should be approved by the Architect and /or Engineer before excavation commences and any approval should be obtained in writing for future reference.
 
Where a grid for setting out is not provided it is sound practice to establish a grid of levels to ensure that the amount of excavated materials is accurately recorded.
 
 

4.1.4 Identify permanent and temporary benchmarks and setting out points

Plans will have been drawn up by the Engineer and Architect which position the structures on the site in an exact orientation and at an exact level. The position and level will have a direct relationship to fixed and immovable points on or around the site which can be re-established during the actual site setting out process. These could be Ordinance Bench Marks (OBM), but are more likely to be local points established and documented on the contract drawings usually referred to as temporary bench marks (TBM).
 
 

4.1.5 Check the setting out points against the setting out information for the works

The required checking on setting out points will be a practical exercise during the two day field study.

 


Task  4.1.1 Setting out Information 

Explain the obligations on the site supervisor and how all relevant information is obtained to ensure that the setting out conforms to requirements.

Word Guide: 300 - 400 
 
 

 


Section 2 Establishing Lines and Levels

Learning outcome: On completion the learner will know how to establish lines and levels for the works.
 

Contents

4.2.1 Relate the setting out information to the circumstances of the site.
4.2.2 Set out lines and levels for construction operations.
4.2.3 Determine the lengths of travellers for excavation and concreting.



4.2.1 Relate the setting out information to the circumstances of the site

This section will be considered in its entirety during the site field course. 
 


4.2.2 Set out lines and levels for construction operations

This section will be covered in practical exercises during the two day practical section of the unit. Although it will be an advantage if you can understand the content and processes before you attend the workshop.
 
The equipment you will need to be able to use is: The first two you will be familiar with one which may be new to you is optical surveying equipment and its use.
 
The following outlines the levelling process and the instruments that will be used during the workshop. It introduces you to the levelling exercise and how levels are booked and recorded.
 
Don’t worry too much if you are having problems understanding this, it will be explained to you on the workshop.
 
 
 
The Levelling Process
 
Optical Level
 
An automatic optical level is essentially a telescope which is used to sight on to a levelling staff. It must be set up so that it is level at all points when swung through 360º. It has controls to adjust focus, slowly traverse/clamp and to increase the definition of the crosshairs (black lines on eyepiece used to read the staff).
 
 
An example of an optical level is shown below.
Optical_Level
Figure 4.2.1 Optical Level


Setting up an Optical Level

Most modern tripods are made of alloy and may have straps tied around the legs for easy transportation. Setting up the tripod involves standing it upright, releasing the screws clamps on the legs and extending the top of the tripod to about the forehead level of the user. The screw clamps are tightened; the legs are spread and pushed firmly into the ground. Selected clamps may now be loosened to allow rough levelling of the top of the tripod and these are of course re-tightened prior to fixing the instrument. The tripod plate should be reasonably level at this point.
 
The level is attached to the tripod using a brass screw thread and handle, which is part of the tripod assembly. The screw housing on the base of the instrument ensures that the instrument is securely fixed, but should never be over tightened.
 
 
 
Key points in levelling the instrument ready for use:

The procedure involved with these processes can be seen by watching the multi-media linked to in the left han column.


 
Levelling Staff
 
A levelling staff or rod is a graduated wooden or aluminium rod, which is graduated to allow the differences in elevation to be determined: An example is shown below.
Staff
Figure 4.2.2 The staff


Reading the Staff
 
A reading is taken through the lens of the instrument onto the rod and the reading of the level is recorded. This is done using the follow steps:  
 
 
Booking the Levels
 
The booking of the levels is done at the same time that a reading is taken. How this is done can be seen by watching the video ‘Recording Level Readings’ in the multimedia box below.
 
There are two methods of booking levels:

Advantages of the two methods of booking:
 
The advantage of the collimation method is that it is ideal for setting out reduced levels on site. The reduced level of points/pegs on site can easily and quickly be found by measuring down (or up, for inverted reduced levels) from the height of collimation.
 
The advantage of the rise and fall method is that it is the simplest method of booking and checking the calculations on site.

Booking_levels
Figure 4.3.3  Taking measurements



Diagrams showing booking Procedure

This survey is booked as shown below. It starts and ends on the same OBM. 

Table_1
Figure 4.2.4  Booking sheet

 

Rules of Booking  
The reducing of the levels using the above rules is shown in Figure 4.2.5 
 
Height_of_Col
Figure 4.2.5  Height of Collimation calculations



Rise and Fall

Rules used when booking levels 
Rise_Fall
Figure 4.2.6 Rise & Fall Calculations

 
To work through this process you should watch the video 'Calculating Rise and Fall' in the multimedia box.



Accuracy Issues

For all types of survey the accuracy of level values should be as follows:  If the closing error exceeds these values the survey should be repeated.

 


Checks on Calculations

Check on reduced levels obtained from back sights and foresights

Sum of back sights - sum of foresights = first reduced level - last reduced level.

 


Rise & Fall

Sum of back sights - sum of foresights = first reduced level - last reduced level = sum of rises - sum of falls = first reduced level - last reduced level. 
 

 

Height of Collimation
 
The Height of Collimation is the height of the line of sight of the instrument over the station above which it is centred, such as the specified datum level or Ordinance Bench Mark (OBM) the way this is calculated is explained in the multimedia presentation entitled ‘Calculating Height of Collimation’ in the multimedia box below.


 


Task  4.2.1 Taking Readings
 
With the use of bullet points, explain the process used in taking readings on a site.

Word Guide: 300 - 400

 

 

4.2.3 Determine the lengths of travellers for excavation and concreting

Where it is intended that the sight rails produced will be used for excavation or construction purposes rather than the use of laser or optical levels the use of a traveller (sometimes referred to as a boning rod) will be required. Accuracy in establishing the length of the boning rod to the depth below the line of sight is essential and relatively easily achieved; (as illustrated below).
Travellers
Figure 4.2.7 Travellers (Click Here to open in a separate window)
 
 
Where excavations will take place which are designed to facilitate sloping construction as in the case of drainage excavations, it is simply a matter of ensuring that the sight rails mirror the fall required and hence the excavation becomes shallower or deeper as the work progresses along the excavation by sighting through the sight rails and leaving the traveller unaltered in length.
 
The basic concept in the use of the boning rod or traveller is that by establishing fixed points at known levels it is a simple procedure to fix a third point by sighting through to others.
 
The traveller is always of a known length, and can be reduced in length as subsequent layers of construction are added.
 


Additional Information

If you would like additional information you can visit the constructionsite unit listed in the column on the left.
 
 
 


Task  4.2.2 Practical Exercise
 
This will be carried out during the attendance workshop
 

 
 

 
Section 3 Inaccurate or Missing Information

Learning outcome: On completion the learner will know how to deal with inaccurate or missing setting out information.

 

Contents

4.3.1 Check that the setting out information in the contract documents is mutually consistent and consistent with the site dimensions.
4.3.2 Inform any interested parties of any inaccurate or missing setting out information.

 
  

4.3.1 Check that the setting out information in the contract documents is mutually consistent and consistent with the site dimensions

Before the site can be set out you will need to ensure that you have all the relevant documents and information and that you have checked to ensure that is consistent and provides sufficient detail to allow the sit/building to be set out correctly. In order to do that you will need to check that:

 


Task  4.3.1 Checking Information Details

Examine the drawings and details provided for this unit which can be seen by clicking on the links in the Drawings for Unit Tasks box above, and determine for the given site, information which is required in order that the setting out can be achieved accurately.

Word Guide: 300 - 400
 
 
 

4.3.2 Inform any interested parties of any inaccurate or missing setting out information

The information should be conveyed to the Architect / Engineer or others responsible for the provision of information by the use of e-mail, memorandum, letter or similar communication system; together with drawings details and illustrations of the required setting out information. You should also inform your line manager as the failure of the Architect/Engineer to provide the information can have an effect on the project.

 

 


Task  4.3.2 Communicating Information

Using the information obtained from Task 1, Communicate with the Engineer/Architect in the above formats requesting the required information.

Word Guide: 300 - 400

 
 


Task  4.3.3 Reflective Account on Unit

Produce a reflective account on what you have learnt in this unit and how it has been of use to you. You should consider what you have learnt; how you have put this into practice and the benefits it has brought to you and your organisation. You can state examples or incidences as a means of illustration.

This task will be completed after the workshop.
 
Word Guide - 800 - 1000 
 

 


Unit Complete
 
You have now completed Unit 4, and you should complete the assignment and send it to info@gatesmacbain.co.uk.

When submitting your assignment you should ensure that it meets all the requirements set out on the Submitting Assignments page, which is accessible from the Student Area or towards the top of the column at the left of this page.

If it does not conform in all respects it will be returned to you and not sent for assessment resulting in delay. ALL questions must be answered in your own words. Any indication of plagiarism will mean that the assignment will fail and be returned to you.

You will be notified as soon as it has been assessed, which will then enable you to continue.